The beginning of the article here is Montazh-metalloCherepy
So, the roof is beautifully and reliably covered by the metallocerepits. However, our roof is warm. So, it needs to be insulated.
In addition to the already installed layer of the membrane, we need to install the heat -insulation slabs close to the membrane between the rafters. For convenient and fast cutting, it is best to use a special knife.
To protect thermal insulation from the steam rising from the house, vapor barrier is needed. A vapor barrier membrane or vapor barrier film is laid on top of thermal insulation plates. Cloths are fastened with brackets with a special pistol overlap. And then connect with a connecting ribbon.
The inner decoration of the attic
It is best to use a chip plate with increased moisture resistance of OSP. The slabs are laid directly along vapor barrier with a long edge along the rafters. Each plate should be based and attached to at least 2 supports. Fix the slabs with self -tapping screws.
Final installation of the drainage system.
So that the drain pipe is not clogged with leaves and other natural garbage, it is recommended to stop the “spider” on top of it from above. On the walls, mark the places of fastening of the drain pipe – 1 holder per 1 meter of pipe. It is best to place them at the joints of the pipes.
Depending on the material of the wall, the pipe holders on wood or on the brick are used.
The knee of the pipe is installed on the final funnel. The pipes are installed in holders and connected using a connecting pipe with the knee. The joints (cuts of pipes) are treated with enamel for polymer coatings.
Pipe fixation is carried out by pipe holders locks.
At the bottom of the pipe, 30 cm from the ground, the drain knee is installed.